A. The VRWJPO Stormwater Management Standard criteria are presented separately below for Post Construction Water Quality, Peak Runoff Rate Control, and Runoff Volume Control:

Post Construction Water Quality

Post construction runoff discharged from a site must meet water quality standards established by the MPCA. Infiltration/filtration options described under Runoff Volume Control Criteria are the preferred approach to satisfying the water quality treatment in areas that drain to the trout stream where such areas do not first drain to a waterbody with 10 or more acres of open water. Permanent wet ponds may fulfill the water quality requirements in areas tributary to designated trout streams, with specified restrictions. Water quality volumes satisfied using infiltration or filtration technologies (filtration only in Type C and D soils) can count toward the Volume Control requirements. Redevelopment projects are required to incorporate water quality best management practices (BMPs) to the extent practical.

Peak Runoff Rate Control

A hydrograph (graph of the water level or rate of flow as a function of time) method based on the most recent precipitation frequency estimates based on scientifically accepted methods and/or applicable federal or state guidance and deemed appropriate by the VRWJPO will be used to analyze runoff for the design or analysis of flows and water levels. 2005 land cover conditions will be applied. Peak runoff rates for proposed activities shall apply land cover conditions existing prior to development and shall not exceed existing runoff rates for the 1-year, 10-year, and 100-year 24- hour duration storm event. Numerical flow standards must be adopted at intercommunity boundaries (where stormwater flows into a community from an upstream community).

Runoff Volume Control

Development that creates one acre or more of new impervious surface (rooftops, driveways, pavement, and other features that impede the infiltration of rainfall) must incorporate volume control practices into the design sufficient to prevent an increase in the runoff volume from the 2-year, 24-hour storm for site conditions prior to development. Determination of the necessary control volume to achieve this Standard is calculated on a site-by-site basis for each activity. Local government units (LGUs) may choose to plan necessary management of stormwater volume on a regional scale (large area, multiple planned developments) or calculate the need on a site-by-site basis for individual proposals.

Runoff volume reducing practices built into site design are the preferred method for meeting volume control. These practices should be considered before designing infiltration or filtration facilities. Practices applying the Minnesota Minimal Impact Design Standards (MIDS) are allowed. The applicant must apply for the credit and provide calculations showing the practice meets the standard.

Specific design requirements for infiltration facilities shall be calculated using appropriate site information and applying design criteria from the Minnesota Stormwater Manual. The function of infiltration facilities is dependent on the ability of soils and underlying materials to allow water to move into the ground (permeability). Constructed infiltration facilities, such as basins and trenches, have several additional requirements.

All stormwater management structures and facilities must be maintained to ensure that they function as originally designed. The responsibility for maintenance is assumed by the LGU with jurisdiction over the facilities or by the applicant in a compliance agreement with the LGU.

Local City/Township Controls

Local ordinances of LGUs may require permits for smaller land disturbing activities and may have stricter controls. Local ordinances may also have specific rate and volume control requirements for redevelopment projects (not solely projects that create new impervious surfaces).