Watershed Standards

The Vermillion River Watershed Management Plan includes Watershed Standards based on state law, watershed-specific conditions, and best practices for water management that establish what local governments must do to provide an acceptable level of water management. Each local government unit must develop a local water management plan and local controls consistent with the Plan and Standards.

The VRWJPO Standards cover six topics:

  • Floodplain alteration
  • Wetland alteration
  • Buffers
  • Erosion and sediment control
  • Stormwater management
  • Drainage alteration

The following sections address frequently asked questions regarding each topic, respectively.

Note: The VRWJPO does not have land-use authority within the watershed. Land-use permitting is administered by the 20 cities and townships within Dakota County under their respective jurisdictions. Scott County issues permits and approvals for projects within its jurisdiction. All applicable local permits and approvals are subject to the VRWJPO Rules, which implement the VRWJPO Standards.

Floodplain Alteration Standards

Q. What are floodplains and why are they important?2026-10-28T17:00:22-05:00

A. A floodplain is the area of land adjacent to a stream channel that is inundated with flood waters during high water periods. Floodplains store water from snowmelt and rainstorm runoff as it moves downstream or as it subsides through infiltration or evapotranspiration. Floodplains are only flooded when a stream overflows its banks. In some areas, they may be inundated on a recurring basis.

Floodplains slow the velocity and reduce the power of floods, protecting downstream areas from flooding or erosive stream velocities. Flooding is a natural process that helps replenish the area’s ecosystem if floodplains connected to the stream during floods.

The term “100-year flood” refers to a flood that has a 1% chance of occurring in any given year. It is not a flood that will occur every 100 years.  The 100-year flood is determined by conducting a hydrologic (flow volumes) and hydraulic (stream characteristics) engineering study. The “100-year flood” is the federal standard for flood protection administration.

Q. Who is involved in floodplain management?2026-10-28T17:00:18-05:00

A. The National Flood Insurance Program (NFIP) was created by Congress in 1968 through the National Flood Insurance Act. Dakota County began participating in the NFIP by adopting a Flood Insurance Study (FIS) and Flood Insurance Rate Maps (FIRMs) in 1973 through the adoption of a Floodplain Management Ordinance. Participation in the NFIP is a city-by-city decision, and all major cities within Dakota County participate. Individual cities adopt a floodplain management ordinance based on standards within the NFIP as well those established by the Minnesota Department of Natural Resources (DNR). Dakota County administers its floodplain management program in all 12 unincorporated townships.

Local floodplain management is accomplished through a three-pronged approach:

  1. The FIS and FIRMs are created by the Federal Emergency Management Agency (FEMA).
  2. The local unit of government adopts the FIS and FIRMs through a local floodplain ordinance which includes prescriptive land use controls to protect the health, safety and welfare of its residents.
  3. The NFIP provides federally-backed flood insurance rates for properties that have been built in or near the FEMA-designated floodplain.

Community specific floodplain maps can be viewed through FEMA’s online Map Service Center. For specific floodplain map and administrative requirements, please contact your city government. Specific questions regarding the floodplain maps or ordinance requirements within unincorporated townships should be directed to the Dakota County Environmental Resources Department at 952-891-7000.

Q. What is floodplain alteration?2026-10-28T17:00:15-05:00

A. Floodplain alteration is any change within the floodplain that affects its ability to accommodate large volumes of water by changing the routing or storage of flood waters. Modified floodplains minimize or completely eliminate the natural functions of the floodplain. Examples include a new building, roadway, fill, or other changes in land use.

Q. When do floodplain alteration requirements come into effect?2026-10-28T17:00:10-05:00

A. Any activity that occurs within the floodplain needs to be reviewed and issued a permit to assure that there is no alteration that would impact the floodplain function. If there would be an impact, a plan for proper mitigation of the impact must be filed as part of the permit application before a permit can be issued.

Contact your city for specific floodplain alteration permit requirements. Within the 13 unincorporated townships, contact the Dakota County Environmental Resources Department.

Q. What are the criteria?2026-10-28T17:00:03-05:00
  • No net stage increase or decrease of more than .5-feet in flood storage capacity to the 100-year flood elevation (1% chance flood event).
  • Where Base Flood Elevations have been established, all new structures shall be constructed with the low floor consistent with the minimum elevations as specified in Minnesota Rule 6120 and consistent with Dakota County and Scott County floodplain ordinances.
  • Projects involving development, redevelopment, or subdivision of land shall establish flood storage, flowage, and drainage easements over areas below the Base Flood Elevation of any public water, public waters wetland, or wetland.
  • Setbacks for floodplain alterations, fill, or underground utilities shall be established and used along watercourses.
    • Where a watercourse has a sinuous flow pattern and a meander belt can be identified, the setback shall be 15 feet from the outer edge of the meander belt.
    • Where a sinuous flow pattern and meander belt are not readily identifiable, the setback shall provide for the potential for restoration and a sinuous flow pattern.
    • Where there are existing encroachments that limit full restoration, the setback shall be 15 feet from the reasonably achievable restoration width for the meander belt.
    • Where full restoration is possible, the setback shall be 15 feet from a meander belt width established along the stream reach that has a width 10 times the bankfull channel width.
    • Where buffers are required, above ground encroachments, alterations, and fill shall be consistent with the prohibited and allowed uses and widths specified in the Buffer Standard.
  • Projects that alter floodplain boundaries and increase upstream water levels are allowed, provided that:
    • The applicant obtains easements or other documentation that demonstrates and records the consent of owners of any lands affected by the increased water levels.
    • The action is consistent with other portions of these Standards and Local, State, and Federal Regulations.
    • The upstream, riparian, and habitat impacts are analyzed, and no detrimental impacts result or are mitigated.

Wetland Alteration Standards

Q. What does wetland alteration mean?2026-10-28T17:00:00-05:00

A. Wetland alteration (or impact) is any action that can change the quantity, quality or functional diversity of a wetland.  Examples of activities that could be wetland alterations include drainage or tiling, filling, excavation, diversion of water to or from the wetland, or changing the types of plants in the wetland.

Wetland alteration and its impacts will be determined by a wetland delineation, which is the process of determining the actual physical boundaries and scientific classification of the wetland by evaluating hydrology (the presence, movement, distribution, and properties of water), vegetation, and soils at the site. Wetland delineation also includes an assessment of the wetland’s ecological functions and value.

Q. When do wetland alteration requirements apply?2026-10-28T16:59:57-05:00

A. Whenever there is a proposed activity (such as drainage or excavation) that changes the hydrology, vegetation or soils within a wetland as governed by the Minnesota Wetland Conservation Act (Minnesota Rules Chapter 8420), as further described below. Useful tip: not all wetlands have standing water/cattails throughout the growing season!

Q. What are the requirements?2026-10-28T16:59:51-05:00

A. Any wetland alteration must comply with the Minnesota Wetland Conservation Act (WCA) and other applicable State and Federal regulations. To ensure compliance, any proposed wetland alterations are advised to have a complete application approved by the acting Local Government Unit (LGU) administering the WCA. A landowner who does not request a decision from the LGU administering the WCA and proceeds with the activity may be subject to enforcement action.

Five general types of WCA applications exist, including: wetland boundary or type applications, no-loss, exemption, sequencing applications, and replacement plan. A landowner is advised to contact the Dakota County Soil and Water Conservation District to determine if a WCA application is required for a proposed land disturbing activity.

If a wetland is being impacted and requires replacement, siting must follow the priority order below:

  1. Mitigation on-site
  2. Mitigation within the same minor subwatershed within the Vermillion River watershed
  3. Mitigation within the VRWJPO boundary
  4. Mitigation within Dakota or Scott County

Transportation projects shall pursue wetland mitigation projects to the extent practical using the criteria above. However, this does not preclude the use of the Minnesota Board of Water & Soil Resources (BWSR) Local Government Road Wetland Replacement Program.

Q. How are wetlands classified?2026-11-02T17:29:50-06:00

Wetlands are classified based on their setting in the landscape (landscape position), source of water, and hydrodynamics (inflow, outflow, flow-through, etc). Regulatory and non-regulatory entities at the state and federal levels have embraced and formally endorsed this system. Details pertaining to each classification type can be seen below.

  • Lacustrine wetlands occur within a topographic depression that has a closed elevation contour that allows the accumulation of surface water and is restricted to the margin of a depressional lake basin.
  • Riverine wetlands occur on a nearly level landform and lie along and is influenced by flooding from a stream, river or flow-through ditch.
  • Slope wetlands occur on a slope (generally >2%) with groundwater discharge as its primary source of hydrology.
  • Mineral flat wetlands occur on a nearly level landform, not significantly influenced by flooding from a stream, river, or flow-through ditch and has predominantly mineral soils.
  • Organic flat wetlands occur on a nearly level landform, not significantly influenced by flooding from a stream, river, or flow-through ditch and has predominantly organic soils.
  • Depression wetlands occur within a topographic depression that has a closed elevation contour that allows the accumulation of surface water and is not associated with the margin of a depressional lake basin.

Definitions excerpted from the BWSR publication “HGM Wetland Classification System for Minnesota (PDF)“.

Buffer Standards

Q. What are some examples of buffer requirements?2026-10-28T16:58:16-05:00

A. Examples include

  • An existing 80-acre parcel is farmed, has no buildings, and has two eligible building sites. The owner sells the property, and the new owner wants to split the property into three new lots, one lot of 77 acres and two lots of 1.5 acres each to use the two building eligibilities. The 77-acre piece will still be farmed, but the other two pieces are going to the new owner’s children to build their houses. The buffer requirement would be in effect on the two 1.5-acre lots if the zoning changes from agricultural to residential, and would not be in effect on the 77-acre parcel, as it would remain zoned agricultural.
  • A 10-acre parcel is going to be split into eight lots, six lots of one acre each and two two-acre lots. The owner is going to build on one of the two-acre lots but is doing nothing with the other lots. The buffer requirement would be in effect on all of the lots unless located in an area zoned agricultural.
  • A parcel of 20 acres was split into 5 lots of 4 acres each about 20 years ago. The owner is going to sell the property. The buffer requirement does not come into effect unless the new owner further subdivides the lots.
  • A 60-acre parcel is farmed and is being split into two parcels, one of 40 acres and one of 20 acres. A house, sheds, and bins are going to be built on about an acre of the 20 acre parcel, but the majority of the 60 acres will continue to be farmed. The buffer requirement would not come into effect if the properties continue to be zoned agricultural and/or continue to be enrolled in Green Acres, Rural Preserves, or Agricultural Preserves.
Q. What can and cannot be done within a buffer?2026-10-28T16:58:28-05:00

A. Once a buffer is established, certain activities within it are allowed and others are prohibited.

Activities allowed within any buffer include:

  • Use and maintenance of a 10-foot-wide unimproved strip through the buffer to access a waterway or wetland.
  • Structures that existed when the buffer was created.
  • Placement, maintenance, repair or replacement of public roads, utilities, and drainage systems that are required as part of subdivision approval or building permit, so long as adverse impacts to the buffer are avoided or minimized to the extent practical.
  • Clearing, grading, and seeding when performed as part of an approved wetland replacement or stream restoration.
  • Construction of underground utilities provided the minimum impact alignment is used, the disturbed area is stabilized, and setbacks are met.
  • Construction of a multipurpose trail through an area protected by conservation easement or in a dedicated outlot, provided erosion and new impervious surface area is minimized, and maintains an absolute minimum distance of at least fifteen feet as measured from the edge of the trail nearest the water resource to the wetland or public waters wetland edge, the bank of the watercourse, or the meander belt, and averages at least one-half the total VRWJPO identified buffer width.

Activities allowed within portions of the average buffer width that exceed the minimum buffer width include:

  • Stormwater management facilities.
  • The area of shallow vegetated infiltration and biofiltration facilities, and water quality ponds not to exceed 50 percent of the pond area, adjacent to wetlands and watercourses may be included in buffer averaging provided the facilities do not encroach into the minimum buffer width.

Prohibited activities include but are not limited to: Building, storage, paving, routine mowing, burning, plowing, introduction of noxious vegetation, cutting, dredging, filling, mining, dumping, grazing livestock, agricultural production, yard waste disposal, or fertilizer application. However, periodic mowing or burning or the use of fertilizers or pesticides for the purpose of managing or maintaining the native vegetation is allowed with the approval of the local government unit. Noxious weeds may be removed by mechanical means or by spot treatment with herbicides, but broadcast treatment is not acceptable.

Q. Where does a buffer start?2026-10-28T16:58:31-05:00

A. Most streams in the Vermillion River Watershed would have the buffer measured beginning at the line of the meander belt. The meander belt is a line connecting the outside points on the same side of a meandering stream bank. Buffers on water quality corridors are measured from the center line of the flow path. Buffers on wetlands begin at the delineated edge of the wetland (the line where hydrology, vegetation, and soils indicate a change between upland and wetland).

Q. Are there exceptions to the buffer requirements?2026-10-28T16:58:34-05:00

A. There are exceptions to the buffer requirements. The primary exceptions are:

  • For any lot that existed prior to the development of the watershed rules (March 2007), the buffer requirement does not apply.
  • For any lot that is created that remains eligible for Green Acres, Rural Preserves, Agricultural Preserves Program, or similar agricultural or rural preservation program, the buffer requirement does not apply.
  • For any wetland area that is filled under an approved Wetland Conservation Act (WCA) replacement plan or a wetland with an applicable WCA exemption, the buffer requirement does not apply.
  • The Buffer Standards do not apply to existing outlots that received preliminary plat approval in the two year period preceding March 22, 2007. Buffer standards in effect at the time of LGU approval of a development agreement shall remain in effect throughout the term of the agreement or for a ten year period from the date of approval, whichever is less.
  • In areas zoned agricultural with one building per every quarter of a quarter section (40 acres), the buffer requirement does not apply until such time that the zoning changes and higher density building eligibilities exist. This exemption does not allow transfer of building eligibility for purposes of clustering.

Note:  35-foot setbacks for structures constructed in agricultural zoned areas should be met to allow for future implementation of the buffer with no impact to structures (i.e. no structural improvements allowed in setback for buffer).

Q. When are buffers required?2026-10-28T16:58:37-05:00

A. Buffers apply when new lots are created by the subdivision of an existing property.

Q. How wide do buffers need to be?2026-10-28T16:58:39-05:00

Buffers need to be wide enough to provide the required protection for the uses the stream should support and the condition of the water and land nearby.  To be most effective, buffers vary in width to address the specific local conditions. However, that approach is impractical to apply and regulate, and it would be very difficult to set guidelines or policies that would fit all situations; each situation would be unique.

VRWJPO conducted a public input and review process to identify classifications for different water resources. This process determined that local conditions could be addressed by setting buffering requirements that would be general, yet still specific enough to provide the necessary protections.  The result is a set of five stream buffer and four wetland buffer classifications. An exhibit is provided on page D-17 in Appendix D of the Watershed Management Plan showing the streams and their designated classification.

Stream classifications:

  • conservation corridor – average 150 feet, minimum 100 feet
  • aquatic corridor principal connector with trout stream designation – 100 feet, no averaging (as required by the Minnesota Pollution Control Agency’s construction stormwater permit)
  • aquatic corridor principal connector – average 100 feet, minimum 65 feet
  • aquatic corridor tributary connector – average 50 feet, minimum 35 feet
  • water quality corridor – average 30 feet, minimum 20 feet

Wetland classifications:

  • exceptional quality – average 50 feet, minimum 30 feet
  • high quality – average 40 feet, minimum 30 feet,
  • medium quality – average 30 feet, minimum 25 feet
  • low quality – average 25 feet, minimum 16.5 feet (one rod)
Q. How is this different than the “Buffer Law”?2026-10-28T16:59:36-05:00

The State of Minnesota enacted a “Buffer Law” in 2015 that requires 50-foot buffers on Department of Natural Resources (DNR) Public Waters and 16.5-foot (one rod) buffers on public ditches. The watershed’s buffer standard does not require placement of buffers immediately, but rather only requires them when properties are subdivided for development. Buffer widths in the Standards are generally wider and affect more types of waterways.

Q. What are buffers and why are they necessary?2026-10-28T16:59:39-05:00

A. In a watershed setting, buffers are bands or strips with permanent vegetation that run adjacent to a stream or wetland.  The purpose of a buffer is to provide a protective barrier or cushion between activities occurring on the upland side of the buffer and the stream or wetland.

Research on riparian (streambank) buffers has shown that appropriately designed buffers protect and improve water quality by intercepting pollutants carried in surface runoff and shallow subsurface water flow.  The riparian zone is an area that is transitional between the land and the water. Although it makes up a small portion of the landscape, it has a critical impact on the water quality in the stream, as well as the number of animal and plant species supported in the landscape.

A healthy and properly buffered riparian zone stabilizes the shoreline or stream bank, provides erosion-control benefits, provides a source of organic matter for aquatic organisms, captures nutrients, reduces flood peak flows, and provides water temperature controls.

Riparian buffers also provide significant habitat benefits, especially for species with a direct relationship to water for food sources or that require either an aquatic or terrestrial environment for certain life stages.

The Vermillion River Watershed Standards define a buffer as an area of natural, minimally maintained, vegetated ground cover abutting or surrounding a watercourse, public waters wetland, or wetland. A property owner is not required to allow public access to a water quality buffer.

Erosion and Sediment Control Standards

Q. What are some techniques to prevent erosion and control sediment?2026-10-28T16:56:41-05:00

A. Among the most commonly used techniques for preventing erosion during land-disturbing activities are:

  • Mulch or hydro-mulch cover
  • Erosion control blankets
  • Ditch liners
  • Riprap
  • Temporary grading, berms, or cat tracking
  • Vegetation

Among the most commonly used techniques for controlling sediment during land-disturbing activities are:

  • Silt fence
  • Fiber rolls (sediment control logs)
  • Hay bale barriers
  • Sediment Traps
  • Buffer Strips
  • Culvert protection

Consult with Dakota County Soil and Water Conservation District or the VRWJPO for assistance with an erosion and sediment control plan.

Q. Why are erosion and sediment control measures important?2026-10-28T16:56:45-05:00

A. Erosion and sediment control measures, used in land development, agriculture, and construction, prevent water pollution and soil loss. The controls often involve the creation of a physical barrier, such as vegetation, silt fence, hay bales, geotextile fabrics such as erosion control blankets, or rock, to absorb some of the energy of the wind or water that could cause erosion and capture sediment before it moves off-site.

Q. What are the criteria?2026-10-28T16:56:48-05:00

A. Erosion and sediment control standards include

  • Erosion and sediment control measures must utilize Best Management Practices (BMPs) and be sufficient to retain sediment on site.
  • All temporary erosion and sediment controls will be installed on all downgradient perimeters before beginning land disturbing activity, and left in place and maintained until the site has been stabilized. All permanent erosion control measures must be installed and operational as shown in the design plans.
  • Erosion and sediment controls shall meet the standards for the MPCA General Construction Stormwater Permit for projects disturbing more than 1 acre.
  • Final stabilization (e.g., seed and blanket) of the site must be completed in accordance with the General Construction Stormwater Permit requirements.
  • All on-site stormwater conveyance channels shall be designed and constructed to withstand the expected velocity of flow from a 10-year frequency storm without erosion.
  • If the activity disturbs more than 1 acre of disturbed area, and the activity is taking place on a site where soils are currently disturbed (e.g., farm field), areas that will not be graded and stabilized as part of the development need to be seeded with a temporary or permanent cover before starting the proposed land disturbing activity.
Q. What projects could require an erosion and sediment control permit?2026-10-28T16:56:52-05:00

A. Land disturbances less than 1 acre of disturbance may require an erosion and sediment control permit by the authority having jurisdiction. If landowners are not certain whether they need this permit, they should consult the LGU or the VRWJPO.

Q. What are erosion and sediment control standards?2026-10-28T16:56:56-05:00

A. The Vermillion River Watershed Joint Powers Organization (VRWJPO) requires permitting for land disturbing activities and/or when projects create new impervious surfaces (roofs, pavement, etc.). Local Government Units (LGUs) in the watershed have adopted ordinances requiring erosion and sediment controls that meet the VRWJPO standards through a building or other permit.

Sites with greater than one acre require a Stormwater Pollution Prevention Plan (SWPPP) for the activity, development, or redevelopment, and must get coverage under the Minnesota Pollution Control Agency (MPCA) General Construction Stormwater Permit in addition to local approvals. For sites disturbing less than one acre and not requiring stormwater facilities on site, an Erosion and Sediment Control Plan may be required by the LGU.

Stormwater Management Standards

Q. What is stormwater management?2026-10-28T16:58:07-05:00

A. A change in the use or management of a piece of land directly impacts how fast or how much water might be moving off the site during or after a rain. Rainfall that collects and moves off a site is called stormwater.  The impacts can be controlled through an evaluation using specific design conditions (modeled storms) and designing elements to slow, store, treat, or eliminate (infiltrate or evaporate) the stormwater. Stormwater management provides runoff rate and volume control as well as water quality treatment.

Q. When do requirements for stormwater management apply?2026-10-28T16:58:00-05:00

A. Projects require permits from the Minnesota Pollution Control Agency (MPCA) with significant provisions for managing stormwater both during and after construction if greater than 1 acre of land is disturbed. Projects generally require the services of qualified engineering and inspection staff for the review, design, and installation oversight required to assure compliance.

Q. What are the criteria?2026-10-28T16:57:57-05:00

A. The VRWJPO Stormwater Management Standard criteria are presented separately below for Post Construction Water Quality, Peak Runoff Rate Control, and Runoff Volume Control:

Post Construction Water Quality

Post construction runoff discharged from a site must meet water quality standards established by the MPCA. Infiltration/filtration options described under Runoff Volume Control Criteria are the preferred approach to satisfying the water quality treatment in areas that drain to the trout stream where such areas do not first drain to a waterbody with 10 or more acres of open water. Permanent wet ponds may fulfill the water quality requirements in areas tributary to designated trout streams, with specified restrictions. Water quality volumes satisfied using infiltration or filtration technologies (filtration only in Type C and D soils) can count toward the Volume Control requirements. Redevelopment projects are required to incorporate water quality best management practices (BMPs) to the extent practical.

Peak Runoff Rate Control

A hydrograph (graph of the water level or rate of flow as a function of time) method based on the most recent precipitation frequency estimates based on scientifically accepted methods and/or applicable federal or state guidance and deemed appropriate by the VRWJPO will be used to analyze runoff for the design or analysis of flows and water levels. 2005 land cover conditions will be applied. Peak runoff rates for proposed activities shall apply land cover conditions existing prior to development and shall not exceed existing runoff rates for the 1-year, 10-year, and 100-year 24- hour duration storm event. Numerical flow standards must be adopted at intercommunity boundaries (where stormwater flows into a community from an upstream community).

Runoff Volume Control

Development that creates one acre or more of new impervious surface (rooftops, driveways, pavement, and other features that impede the infiltration of rainfall) must incorporate volume control practices into the design sufficient to prevent an increase in the runoff volume from the 2-year, 24-hour storm for site conditions prior to development. Determination of the necessary control volume to achieve this Standard is calculated on a site-by-site basis for each activity. Local government units (LGUs) may choose to plan necessary management of stormwater volume on a regional scale (large area, multiple planned developments) or calculate the need on a site-by-site basis for individual proposals.

Runoff volume reducing practices built into site design are the preferred method for meeting volume control. These practices should be considered before designing infiltration or filtration facilities. Practices applying the Minnesota Minimal Impact Design Standards (MIDS) are allowed. The applicant must apply for the credit and provide calculations showing the practice meets the standard.

Specific design requirements for infiltration facilities shall be calculated using appropriate site information and applying design criteria from the Minnesota Stormwater Manual. The function of infiltration facilities is dependent on the ability of soils and underlying materials to allow water to move into the ground (permeability). Constructed infiltration facilities, such as basins and trenches, have several additional requirements.

All stormwater management structures and facilities must be maintained to ensure that they function as originally designed. The responsibility for maintenance is assumed by the LGU with jurisdiction over the facilities or by the applicant in a compliance agreement with the LGU.

Local City/Township Controls

Local ordinances of LGUs may require permits for smaller land disturbing activities and may have stricter controls. Local ordinances may also have specific rate and volume control requirements for redevelopment projects (not solely projects that create new impervious surfaces).

Drainage Alteration Standards

Q. What does drainage alteration mean?2026-10-28T16:57:53-05:00

A. Drainage alteration refers to a change in the natural course of water flow as it moves through the watershed.  Drainage alteration may take the form of creating artificial drainage, pumping, diverting, obstructing (impounding or damming), channeling, or otherwise modifying the natural process of water movement through the landscape.

If drainage alteration is proposed, the Local Government Unit (LGU) should review the proposed drainage alteration as part of subdivision review, building permits, grading permits, or other applicable local controls. LGUs should provide land alteration plans with proposed drainage alterations to the Vermillion River Watershed Joint Powers Organization (VRWJPO) and are encouraged to coordinate with VRWJPO staff regarding drainage alteration concerns and applicable standards.

Q. When do requirements about drainage alteration apply?2026-10-28T16:57:45-05:00

A. Drainage alteration requirements apply when:

  1. An outlet is being proposed for a landlocked basin with a contributing area of 100 acres or more; or
  2. A drainage alteration is being proposed for a watercourse, public water, public water wetland, or wetlands that drain 640 acres or more.
Q. What are the criteria in the standard?2026-10-28T16:57:01-05:00

A. For draining landlocked basins:

  1. Outlets are consistent with other portions of the VRWJPO Standards, as well as other local, state, and federal regulations.
  2. Analysis is completed of potential downstream, riparian, and habitat impacts of outlets; implementation results in no detrimental impact to property or natural resources.
  3. Runoff analysis for flows and water levels are based on a hydrograph method. A hydrograph is a graph showing changes in water flow or water level over time.
  4. The proposed post-installation hydrology (water distribution and movement) is consistent with peak runoff rate and volume controls.
  5. The outlet does not create adverse downstream flooding or water quality conditions, or affect stability of downstream water courses.
  6. The outlet maintains dead water storage, a volume with little to no current, in a basin or channel to the extent possible.
  7. Development contributing runoff to a landlocked basin incorporates best management practices to reduce the runoff volume to the extent possible.

For proposed alteration of waterways, public waters, public waters wetlands, or wetlands:

  1. Alterations or diversions are consistent with other portions of the VRWJPO Standards, as well as other local, state, and federal regulations.
  2. Analysis of potential downstream, riparian, or habitat impacts of alterations or diversions are completed and predict no detrimental impacts.
  3. The proposal demonstrates a reasonable necessity for the alteration or diversion to improve or protect public health and safety or to improve or protect aquatic resources.
  4. Unnecessary injury to upstream or downstream lands is avoided.
  5. The alteration provides greater benefit (positive impacts of drainage, dam or diversion) than harm (costs) to lands affected by the alteration.
  6. The alteration benefits the natural hydrologic system by returning, restoring, or maintaining its natural capacities.

All drainage alterations, diversions, and landlocked basin outlets shall be provided with stable outfalls and channels designed to withstand erosion during the 10-year, 24-hour precipitation event.

Q. Are there exceptions?2026-10-28T16:56:58-05:00

A. The LGU or VRWJPO may waive the evaluation of impacts if:

  1. The landowner can demonstrate that the proposed drainage alteration will cause no off-site impacts (erosion, sedimentation, flooding, or other damage); or
  2. The landowner provides proof of the consent of potentially impacted landowners through easements or other documentation (in a form acceptable to the LGU or VRWJPO).